To provide meaningful oversight of OCPA's efforts to monitor, measure, report, and control the market and credit risks that it is exposed to in its normal course of business, OCPA's board should amend its risk management policy to alter the membership of the risk oversight committee to include a limited subset of OCPA board members that does not violate open meeting act requirements.
6-Month Agency Response
During 3-15-2023 Board meeting this recommendation was discussed by the Board and concerns regarding the Brown act were raised.
At the 4-19-2023 Board meeting item 9.3 was presented to the Board. The item discusses quarterly meetings and the responsibilities of the Risk Oversight Committee.
Although the Board decided not to add board members to the committee it agreed with staff and legal counsel's recommendation to invite both Board Chair and VC to future meetings as observers.
Orange County Power Authority Board Regular Meeting March 15, 2023 (vimeo.com). The conversation regarding the ROC begins at 1:15.37.
- Completion Date: May 2023
- Response Date: August 2023
California State Auditor's Assessment of 6-Month Status: Resolved
In April 2023, the CEO reported to the OCPA board that, as an alternative to our recommendation, beginning in April 2023 he initiated a practice of inviting the chair and vice chair of the OCPA board to observe risk oversight committee meetings. According to OCPA, its legal counsel determined that including a limited subset of OCPA board members on the risk oversight committee would make its meetings subject to open meeting act requirements. Based on its legal counsel's determination we consider this recommendation to be resolved.
- Auditee did not address all aspects of the recommendation
60-Day Agency Response
OCPA has developed an Improvement Plan to address each recommendation. In accordance with the Improvement Plan, this recommendation will be completed as of May 2023.
- Estimated Completion Date: May 2023
- Response Date: April 2023
California State Auditor's Assessment of 60-Day Status: Pending
OCPA has not yet submitted evidence demonstrating it has implemented this recommendation.