Report 2011-504 Recommendation 22 Responses
Report 2011-504: High-Speed Rail Authority Follow-Up: Although the Authority Addressed Some of Our Prior Concerns, Its Funding Situation Has Become Increasingly Risky and the Authority's Weak Oversight Persists (Release Date: January 2012)
Recommendation #22 To: High-Speed Rail Authority, California
To effectively manage its contracts, the Authority should begin awarding contracts with a sufficient amount of lead time.
6-Month Agency Response
The Authority provided a schedule of contract expiration dates to ensure that contract managers receive timely notifications from the contract unit of contract expiration dates. Additionally, the Authority asserted that its contract manual contains language ensuring adequate lead time in the contract award process. (See 2013-406, p. 247)
- Response Date: August 2012
California State Auditor's Assessment of 6-Month Status: Fully Implemented
All Recommendations in 2011-504