Report 2015-117 Recommendations
When an audit is completed and a report is issued, auditees must provide the State Auditor with information regarding their progress in implementing recommendations from our reports at three intervals from the release of the report: 60 days, six months, and one year. Additionally, Senate Bill 1452 (Chapter 452, Statutes of 2006), requires auditees who have not implemented recommendations after one year, to report to us and to the Legislature why they have not implemented them or to state when they intend to implement them. Below, is a listing of each recommendation the State Auditor made in the report referenced and a link to the most recent response from the auditee addressing their progress in implementing the recommendation and the State Auditor's assessment of auditee's response based on our review of the supporting documentation.
Recommendations in Report 2015-117: California Department of General Services' Real Estate Services Division: To Better Serve Its Client Agencies, It Needs to Track and Analyze Project Data and Improve Its Management Practices (Release Date: March 2016)
Recommendations to General Services, Department of | ||
---|---|---|
Number | Recommendation | Status |
2 | To ensure long-term efficient and effective delivery of projects, the division, in its planned implementation of its new project management system in July 2017, should ensure that the project management system can centrally track and extract all data regarding project status, including time delays, cost overages, and the reasons for each. |
Pending |
3 | To ensure long-term efficient and effective delivery of projects, the division, in its planned implementation of its new project management system in July 2017, should track the reasons that projects are pending to identify its true backlog of projects. In doing so, it should develop a process to follow up on those projects that are pending to ensure that they are not on hold unnecessarily and are appropriately moving forward. |
Pending |
4 | To ensure long-term efficient and effective delivery of projects, the division, in its planned implementation of its new project management system in July 2017, should, at least annually, use the centrally tracked data to identify common themes in the causes for project delays and cost overages and develop solutions to address these issues. Further, it should report the results of its review to General Services' executive management. |
Pending |
5 | Until the division implements its planned project management system, it should, by September 2016, develop a process to, at a minimum, identify project status and reasons for project delays as well as cost overages. Using these data, the division should modify its project management processes to ensure the efficient and effective delivery of projects. |
Will Not Implement |
6 | The division should develop and implement a process for preparing reasonable time frames and cost estimates for its projects within the building management branch. To better inform the development of this process, the division should evaluate the branch's structure, which should include a staffing analysis, to determine whether it is effectively organized and whether it should add cost estimator positions. |
Will Not Implement |
7 | To ensure that client agencies are paying equitable rates, by December 2016 General Services should develop and implement a strategy for allocating its administrative costs equally among all the projects it completes for client agencies, including those portions outsourced to private firms. |
Will Not Implement |
8 | To ensure that the project management branch charges its client agencies a competitive hourly rate, by December 2016 and every two years thereafter, the division should conduct a rate analysis that fully accounts for differences between the project management branch's rate and private firms' rates. If it finds that the rates are not competitive, the division should identify and implement strategies to ensure that the project management branch's rates are as competitive as they can be with those of its private firm counterparts. Further, the division should explore and implement any other reasonable methods to ensure that it is delivering projects as cost effectively as possible. |
Will Not Implement |
9 | To improve its communication with client agencies, the division should ensure that project managers are using consistent procedures by providing specific expectations related to communicating and documenting time delays, cost changes, and change orders, at a minimum. |
Fully Implemented |
10 | To improve its communication with client agencies, the division should develop a process for providing periodic detailed bills and invoices to client agencies clearly describing the work for which it is charging. |
Pending |
11 | To effectively evaluate the performance of its branches in delivering projects, the division should develop meaningful goals and objectives and a method of measuring its success in achieving them as part of its strategic plan that is focused on ensuring that projects are delivered on time and within budgeted cost estimates. |
Will Not Implement |
12 | To ensure that its project management staff are adequately trained and have the information necessary to deliver projects as efficiently and effectively as possible, the division should conduct a comprehensive survey every other year of all of its client agencies to inform necessary improvements to its processes and training program and, in the interest of transparency, make the survey results public. |
Will Not Implement |
13 | To ensure that its project management staff are adequately trained and have the information necessary to deliver projects as efficiently and effectively as possible, the division should develop and implement by December 2016 a periodic training program for staff within its project management and building management branches. This training program should include updated information that reflects any processes it revises based on its review of critical project status data and its progress toward meeting its goals. |
Fully Implemented |
Recommendations to Legislature | ||
---|---|---|
Number | Recommendation | Status |
1 | To improve efficiencies and reduce some costs for less complex and easily repeatable projects, the Legislature should authorize the division to create and implement a pilot program for job order contracting for appropriate projects, including a requirement that the division award contracts to the most qualified responsive bidders. The division should report to the Legislature on its progress within two years of implementing the pilot program, including, at a minimum, information regarding the time and cost savings the pilot program provided the State. |
Legislation Proposed But Not Enacted |