Report 2023-302 Recommendation 4 Responses
Report 2023-302: Judicial Branch Procurement: Judicial Council of California (Release Date: January 2024)
Recommendation #4 To: Judicial Council of California
By June 2024, the Judicial Council should ensure that procurement staff receive the revised training it develops to clarify the following: the correct type of solicitation process to use when procuring IT goods and services.
6-Month Agency Response
The Judicial Council's procurement team has completed development of training material and is scheduled to provide the recommended training during July 2024.
- Estimated Completion Date: July 2024
- Response Date: July 2024
California State Auditor's Assessment of 6-Month Status: Pending
60-Day Agency Response
The Judicial Council's procurement team is on track to provide the recommended training to staff by the end of June 2024.
- Estimated Completion Date: June 2024
- Response Date: March 2024
California State Auditor's Assessment of 60-Day Status: Pending