Report 2017-118 Recommendation 3 Responses
Report 2017-118: State and Regional Water Boards: They Must Do More to Ensure That Local Jurisdictions' Costs to Reduce Storm Water Pollution Are Necessary and Appropriate (Release Date: March 2018)
Recommendation #3 To: Central Valley Regional Water Quality Control Board
Once the State Water Board has developed cost-estimation guidance, the regional boards should follow this guidance.
1-Year Agency Response
The Central Valley Regional Water Board will follow the guidance developed by the State Water Board.
- Completion Date: March 2019
- Response Date: February 2019
California State Auditor's Assessment of 1-Year Status: Fully Implemented
6-Month Agency Response
The Central Valley Regional Water Board will follow the guidance once it is developed.
- Estimated Completion Date: To be determined.
- Response Date: August 2018
California State Auditor's Assessment of 6-Month Status: Pending
60-Day Agency Response
The Central Valley Regional Water Board will follow the guidance once it is developed.
- Estimated Completion Date: Timeline in development.
- Response Date: April 2018
California State Auditor's Assessment of 60-Day Status: Pending
All Recommendations in 2017-118
Agency responses received are posted verbatim.