Report 2014-116 Recommendation 19 Responses
Report 2014-116: California Department of Consumer Affairs' BreEZe System: Inadequate Planning and Oversight Led to Implementation at Far Fewer Regulatory Entities at a Significantly Higher Cost (Release Date: February 2015)
Recommendation #19 To: Consumer Affairs, Department of
If Consumer Affairs determines that a new IT project is warranted in the future, it should develop a process to ensure the success of that project that includes, at a minimum, a project team that is qualified and experienced.
Annual Follow-Up Agency Response From October 2016
The California Department of Technology has implemented a revised Project Approval Lifecycle (SIMM 19), which includes a four stage project review and approval process. Stage 4 of this approval process requires Department of Technology review and approval of project resources to ensure that they are available and properly qualified, experienced, and trained (SAM 4928 - Information Technology). As the Department's IT projects fall under the Department of Technology's purview, the revised Project Approval Lifecycle will ensure that any future IT project at the Department includes a project team that is qualified and experienced. With the release of Technology Letter 16-07 in August 2016, all four Stages of the Project Approval Lifecycle are complete and in place.
- Completion Date: August 2016
California State Auditor's Assessment of Annual Follow-Up Status: Fully Implemented
1-Year Agency Response
The California Department of Technology has implemented a revised Project Approval Lifecycle (SIMM 19), which includes a four stage project review and approval process. Stage 4 of this approval process requires Department of Technology review and approval of project resources to ensure that they are available and properly qualified, experienced, and trained (SAM 4928 - Information Technology). As the Department's IT projects fall under the Department of Technology's purview, the revised Project Approval Lifecycle will ensure that any future IT project at the Department includes a project team that is qualified and experienced.
- Completion Date: October 2015
- Response Date: February 2016
California State Auditor's Assessment of 1-Year Status: Pending
According to the Department of Technology's one-year response to recommendations eight through ten regarding its four stage project review and approval process, Stage 4 of that approval process is scheduled for final release in July 2016. Thus, until that stage is finalized and includes steps to ensure that any future IT project includes a project team that is qualified and experienced, we will continue to report the status of this recommendation as pending.
- Auditee did not substantiate its claim of full implementation
6-Month Agency Response
The Department has implemented additional procedures for IT projects based on lessons learned. For any new IT project, a project staffing plan will be required prior to embarking on the project. At a minimum, the components of the project staffing plan will include the number of staff required, how staff will be acquired, length of time the staff will be needed, qualifications, skills, and training needs.
- Completion Date: July 2015
- Response Date: August 2015
California State Auditor's Assessment of 6-Month Status: Pending
Until Consumer Affairs develops a formal process to ensure that, at a minimum, its project team that oversees any new IT project is qualified and experienced, we will not consider this recommendation fully implemented. According to Consumer Affairs, it plans to provide us with a status update on its implementation of this recommendation in its one-year response
- Auditee did not substantiate its claim of full implementation
60-Day Agency Response
The Department will develop a project staffing plan prior to embarking on any new IT project. Items that will be included in the project staffing plan are the number of staff required, how staff will be acquired, length of time the staff will be needed, qualifications, skills, and training needs.
- Estimated Completion Date: TBD
- Response Date: April 2015
California State Auditor's Assessment of 60-Day Status: No Action Taken
We followed-up with Consumer Affairs on the status of this recommendation as reported in its 60-day response, and learned that it intends on developing a plan that will include activities that address this recommendation after it implements BreEZe at the phase 2 regulatory entities.
All Recommendations in 2014-116
Agency responses received are posted verbatim.