Report 2011-123 Recommendation 6 Responses
Report 2011-123: Oil Spill Prevention and Administration Fund: The Department of Fish and Game and the Office of Spill Prevention and Response Need to Improve Their Administration of the Spill Fund (Release Date: August 2012)
Recommendation #6 To: Spill Prevention and Response, Office of
To ensure that the spill office continues to work consistently with other entities to resolve issues with the use of staff and equipment and that it has the necessary resources to carry out its operations, the spill office should develop written policies and procedures with Fish and Game enforcement regarding staffing decisions.
1-Year Agency Response
Coordination guidelines have been signed and adopted between OSPR and CDFW Enforcement. The guidelines are currently being implemented.
- Completion Date: March 2013
- Response Date: August 2013
California State Auditor's Assessment of 1-Year Status: Fully Implemented
6-Month Agency Response
The department stated that coordination guidelines have been signed and adopted between OSPR and CDFW Enforcement. The department also stated that the guidelines are currently being implemented.
- Response Date: May 2013
California State Auditor's Assessment of 6-Month Status: Pending
The department's six-month response was submitted three months late. In addition, no documents were provided to support its assertion that the recommendation was fully implemented. The department agreed to provide this documentation as part of its one-year response.
60-Day Agency Response
Fish and Game explained that it has completed draft guidelines regarding the coordination of the spill office and Fish and Game enforcement and the current target for adoption of these guidelines is January 1, 2013. (See 2013-406, p. 213)
- Response Date: October 2012
California State Auditor's Assessment of 60-Day Status: Pending
All Recommendations in 2011-123
Agency responses received after June 2013 are posted verbatim.