Report 2010-102 Recommendation 37 Responses
Report 2010-102: Administrative Office of the Courts: The Statewide Case Management Project Faces Significant Challenges Due to Poor Project Management (Release Date: February 2011)
Recommendation #37 To: Administrative Office of the Courts
To ensure that future major IT projects receive appropriate independent oversight over technical aspects and project management, the AOC should address promptly and appropriately the concerns that independent oversight consultants raise.
1-Year Agency Response
The AOC stated it concurs with the importance of the identification of concerns raised by IV&V and IPO consultants and that their concerns be reported and monitored to ensure they are appropriately addressed. The AOC also stated concerns raised by IV&V and IPO consultants will be taken off watch status only after careful consideration and discussion of all risks and mitigation efforts that must occur to ensure that system function is unaffected. (See 2013-406, p. 145)
- Response Date: November 2012
California State Auditor's Assessment of 1-Year Status: Fully Implemented