Report 2010-102 Recommendation 32 Responses
Report 2010-102: Administrative Office of the Courts: The Statewide Case Management Project Faces Significant Challenges Due to Poor Project Management (Release Date: February 2011)
Recommendation #32 To: Administrative Office of the Courts
To ensure that no gaps in oversight occur between CCMS development and deployment, the AOC should ensure that it has IV&V and IPO services in place for the deployment phase of CCMS. Further, to allow for independent oversight of the IV&V consultant, the AOC should use separate consultants to provide IV&V and IPO services.
1-Year Agency Response
In March 2012 the Judicial Council voted to halt deployment of CCMS; thus, this recommendation is no longer relevant. (See 2013-406, p. 144)
- Response Date: November 2012
California State Auditor's Assessment of 1-Year Status: Will Not Implement
All Recommendations in 2010-102