Report 2010-102 Recommendation 22 Responses
Report 2010-102: Administrative Office of the Courts: The Statewide Case Management Project Faces Significant Challenges Due to Poor Project Management (Release Date: February 2011)
Recommendation #22 To: Administrative Office of the Courts
The AOC should require superior courts to identify their past and future costs related to the project, particularly the likely significant costs that superior courts will incur during CCMS deployment, and include these costs in the total cost.
1-Year Agency Response
In March 2012 the Judicial Council voted to halt deployment of CCMS; thus, this recommendation is no longer relevant. (See 2013-406, p. 134)
- Response Date: November 2012
California State Auditor's Assessment of 1-Year Status: Will Not Implement
All Recommendations in 2010-102
Agency responses received after June 2013 are posted verbatim.